Hogeweidebridge

The Hogeweide Bridge has with the required temporary steel a
weight of about 3000 tons. During a weekend the bridge was
floated to its final position. This 24 hour operation was the
culmination of 2 years of work. The bridge was fabricated and
assembled in Eeklo and Gent and brought to site by water in
pieces weighing up to 700 tons for final assembly on site. The
Hogeweide Bridge lies between the Prins Claus Bridge and the
Demka Bridge, both also built by Victor Buyck.

Project at 
a glance

LOCATION

Netherlands Utrecht

STRUCTURE

Road bridge

CLIENT

Gemeente Utrecht

PROPORTIONS

170m x 26m

WEIGHT

2.200

START

09/2005

FINISHED

09/2007